For Quality Concrete Around the Home, We Recommend...
1. Planning: A. Thickness: 4 inches is generally enough for parking areas and driveways. Depending upon traffic use, thicker sections may be required. Typically rebar or wire mesh is not needed for driveways and sidewalks that are 4" or less in depth. Check with your local municipality for exact building code. B. Base: Compacted earth may be entirely adequate as a base for residential concrete; however, where expansive clays are present a select base material ,such as sand, should be imported.
C. Drainage: Surface of the finished slab should slope at least 1/8 inch per foot away from structures. A slope of 1/4 inch per foot is best.
2. Preparation: A. Excavating: Be sure to take out all organic matter sludge, leaves, tree roots, wood, etc. Don't dig deeper than you need to. B. Compaction: Soil on which concrete is to be placed must be compacted uniformly and evenly so the slab won't settle and won't vary in thickness. Use sand to fill in the low spots as necessary. C. Forms: Stake securely with a slope of 1/4 inch per foot is best drainage capabilities. Scrape loose base away from forms so edges will be at at least full thickness. Walkways should be 4" thick with driveways or other slabs 6" thick. You can form a 4" slab with 2x4's and a 6" slab with 2x6's. Do not use press board or fiberboard for forms. These types of forms ALWAYS lead to concrete blowouts and more work on your part to repair and finish your concrete. If you need to build a form over 8" tall we recommend using 1/2" or 3/4" plywood with supports every 18-24" to prevent bowing and blowouts.
D. Isolation: Before concrete is delivered, install pre molded joint material wherever flatwork comes against buildings, steps, walls, existing slabs, etc. This is so the new concrete slab will be separated from the structures and allows for expansion and contraction of concrete in the changing seasons. Joint material must extend all the way to the bottom of the slab. Liquid nail is a good way to adhere the expansion material to existing concrete. This should be done to allow for the liquid nail to dry before the concrete is delivered.
3. Specifications For Concrete: A. Strength: Concrete placed in slabs exposed to freezing and thawing should have a minimum 28 day compressive strength of 3500 psi and have at least 5, plus or minus 1.5% entrained air.
B. Slump: Slump should be 4 in.+/- 1 in. A slump greater than 4" will prolong the time you have to wait before finishing, particularly in cool weather. It will also increase the tendency for shrinkage cracking.
C. Chemical Admixtures: In addition to air entraining admixtures, chemical admixtures in conformance with ASTM C-494 may be used to accelerate or retard setting, reduce water or plasticize the concrete.
4. Placing: A. Filling the Forms: Chute, wheel or shovel concrete directly to its final position. Don't dump it in piles and then flow, drag or rake it the rest of the way.
B. Leveling: Screed (strike off) to level the surface. Immediately use wood or Mag Bull Float to take out small high and low spots. This can also be done by pulling a 2x4 back and forth motion over top of the forms. Then, stop working on that portion of the slab until bleed water (water sheen) disappears from surface.
5. Finishing: A. When to Finish: Immediately after all the bleed water (water sheen) is gone, joint, edge and texture as required.
B. Final Finish: A broom finish is recommended particularly on driveways, walks, and other exterior areas. Machine floating and the use of a steel trowel are not recommended for exterior surfaces.
C. Joints: Control joints may be hand tooled or sawed. In either method, they must be cut to a depth of at least 1/4 the thickness of the slab and spaced so that the dimension either direction does not exceed that shown in the following table.
Minimum distance between joints
Maximum distance between joints.
Preferred distance between joints
Patio or Driveway
(usually 6" thick)
10 feet, 5 inches
12 feet. Not to exceed 1.5 times the width of the pad.
Divide the slab into squares when possible. 12 foot squares are preferable.
Sidewalks
(usually 4" thick)
Same as the width of the pad. For a 2 foot wide pad the minimum distance between joints is 2 feet.
5 feet. Not to exceed 1.5 times the width of the pad.
For sidewalks shorter than 5 feet divide in half. Squares are preferable and look best.
Local codes or ordinances govern, check codes with your local municipality. Joints must be straight and continuous; not staggered or offset. When control joints are sawed, this should be done after all other finishing and curing applications are complete and as soon as the concrete has hardened sufficiently to permit sawing without raveling. D. Caution: Over finishing is the major cause in surface deterioration, therefore do not overwork the surface. Not only is it time consuming and expensive, but tends to bring too much fine material to the surface and weaken it. Never use a steel trowel on concrete exposed to weather. E. Curing: Apply curing as soon after final texturing as it can be done without marring the surface.
6. Curing: A. Need for Curing: Curing is one of the most important steps in concrete construction and regrettably, one of the most neglected. Effective curing is absolutely essential for surface durability. Fresh concrete must be kept warm and moist until the mixing water combines chemically with the cement (hydration). That's what hardens the concrete and gives it its strength. Uncured concrete will have a weak surface which may deteriorate when exposed to freezing and thawing.
B. Curing in Warm Weather: Curing can be accomplished in a number of ways, but the simplest, and most widely used method is a liquid membrane (meeting ASTM-309 standards) which is sprayed or rolled on the surface of a slab as soon as practical after finishing to prevent premature drying of the surface. This must be applied at a rate not thinner than manufacturer's instructions. For example, many specify a coverage of not more than 200 square feet per gallon (that's twice as thick as you would apply most house paints. Water can be used when you are able to insure constant wetting for 3 days.
C. Curing in Cold Weather: It is absolutely essential that fresh concrete be kept from freezing for at least the first week after it is placed. Membrane curing does not keep the concrete warm enough nor does calcium chloride accelerator prevent concrete from freezing. Only adequate insulation or heating will maintain proper curing temperatures during freezing weather.
D. What Not to Use: Avoid any curing method that lets the surface dry in a short time. Quick drying stops the hardening process, thus making a weak surface that is likely to scale.
E. Drying: After curing, newly placed outdoor concrete needs time to dry in warm air. Concrete placed early enough in the season so that it has one month of temperatures above 40 degrees F for curing and still another month for drying out before hard freezes are expected. Dried concrete has a decided advantage over concrete that has not dried out when cold weather begins.
7. Tips to Owners: A. First Winter: Do not use salt or other deicers during the first winter. Use sand instead to improve traction. Even light applications of salt, or salt carried on cars may cause severe scaling of newly placed concrete. Fertilizers are not an acceptable deicer at any time.
B. Saturation: Proper drainage should be maintained to avoid saturation of concrete.
C. Sealing and Curing are not the Same: Sealers are water repellant coatings that can help prevent damage from freeze/thaw cycles and salting. They deter water from getting into the surface pores. Curing is the process of the concrete drying to reach its maximum strength. Newly cured concrete should have a period of air drying before being sealed, at least three to four weeks. Allow driveways to cure for two to three weeks before parking or driving on them. Following these easy steps, concrete will provide many years of trouble free service.
CAUTION: MAY CAUSE EYE OR SKIN INJURY Frontier Ready- Mix Concrete contains Portland cement. If any cement or cement mixtures get into the eye, flush immediately and repeatedly with water and consult a physician promptly. Freshly mixed, cement, mortar, concrete or grout may cause skin injury. Avoid contact with skin where possible and wash exposed skin areas promptly with water. For the Material Safety Data Sheet on Portland Cement click here.
Small Load Specialist
Call to see how we can save you time and money with a superior quality concrete.
801-782-9783
For a complete video on how to properly form, prep, and finish your concrete Click Here.